NordLink
Since April 2018 is De Romein Group on behalf of NKT Cables Group, working on the realisation of the NordLink land cable section.
In the period April 2018 to March 2019, we worked out the complete 54- kilometre route on paper for the purpose of obtaining the final planning permission. After this preparatory work, we took the implemetation design on the basis of the permit design and perpared it for implementation.
In the spring of 2019, we started to carry out the work effectively. In addition to digging the trench for retracting the cables over a length of about 31 kilometers, we drilled the route over a length of about 23 kilometers, in lenghts ranging from 60 to about 600 meters (crossing with the Nord Ostsee Kanal).
For the purpose of making the project accessible and keeping the project accessible, construction roads have been built over a length about 50 kilometers of roadplates from steel and wood.